A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:

a) 9 days
b) 10 days
c) 11 days
d) 12 days

Answer: c
Explanation: Work rate of A = $$\frac{{100}}{9}$$ = 11.11% work per day
Work rate of B = $$\frac{{100}}{{15}}$$ = 6.66% work per day
They together can do (A + B) = 11.11 + 6.66 ≈ 18% work per day
They are working in alternate day, so we take 2 days = 1 unit of day
Therefore, in one unit of day they can complete 18% of work
(A + B) can complete 90% of work in 5 units of days. i.e. (5 × 18)
And the rest 10% work will be completed by A in Next day
Total number of day = 5 Unit of days + 1 day of A
= 2 × 5 + 1 = 11 days